Thompson School District

Bedrock Slingers playground renovation project to create an ADA accessible playground replacing sand with pea gravel and EWF for safe, easily accessible play for all students.

 

Client: Thompson School District

Location: Ivy Stockwell Elementary, Berthoud, CO

Service: Playground Renovation

Details: During a four-day playground renovation project to create an ADA accessible playground, we removed 15 inches of sand, then installed 6 dry wells for drainage, placed 3 inches of pea gravel, and topped it off with 750 cubic yards of EWF for safe, easily accessible play for all students.